Water Treatment Plant - Ouray, CO


“Spears fabricating our PVC fittings saved us a great deal of time in the fabrication department. We could focus on other parts of fabrication while our fittings were being built. We have already started using Spears to build other fittings for other projects, and will continue to do so.”

-Austin M.

Details about the project.

Project name: Town of Ouray Colorado

Project manager: Pedro Ore Grillo

Project draftsman: Pedro Ore Grillo, Austin Moore

Project engineer: Deb Jensen (President of Filter Tech Systems)

Quantity of Spears fabricated fittings: 35

Skids using fabricated fittings: 5

Skid names:

                -The Xiga Skids used 9 fabricated fittings each. There are a total of 3 Xiga skids. They are the largest skids and the ones with the 20’ long horizontal housings, as well as the tall vertical piping.

                -The Pre-strainer skid used 2 fittings total. This skid had the 2 large stainless steel filters on top of them.

                -The Backwash Pump Skid used 2 fittings total. This skid has the 3 large 60HP pumps on the skid.

                -There were 4 more fittings fabricated to go in between the Xiga skids as connection piping that we currently do not have pictures of, but can easily be obtained.